1. Put the gabion nets in place with staggered seams to avoid longitudinal through seams;
2. Stand up the four sides of the gabion net, and lock the adjacent edges with the tie line. When tying the lock, wrap the tie line around the two overlapping frame lines (when stitching the edges) or the double twisted side of the frame line and the net cage (When sewing the grille) Tighten spirally to avoid heavy galvanizing damage, and the pitch is not more than 50 mm;
3. When the gabion net is installed on the completed bottom net, the gabion net should be fixed to the bottom gabion net along the lower frame of the newly installed gabion net with the binding wire. Prison, so that the stone cage net is connected into one;
4. When constructing at the same level of a certain unit project, the gabion nets should be fully in place before filling the pebbles. In order to prevent the deformation of the gabion nets, two adjacent gabions The height difference of the filling stone of the cell should not be greater than 35 cm;
5.Before the gabion net is installed, the bank slope and the ground should be properly trimmed, and the original shape of the bank slope should be maintained as much as possible, but there should be no obvious uplifts and depressions;
6. The filled pebbles are selected on the floodplain, and their compressive strength should meet the design requirements. The particle size of the pebbles should be between 8-20 cm, and the size should be reasonably matched to achieve the design requirements of the porosity and ensure the straight line of the gabion net shape;
7. When filling pebbles in the gabion net, use pebbles with a particle size of not less than 10 cm on the exposed surface, and artificially lay it out to obtain a beautiful surface and prevent water flow from washing away the pebbles from the mesh. The height of the super-filled stone should be 2.5~3 cm in order to leave room for subsidence;
8. After the gabion net is filled with stones, the top cover will be lowered, and then the two overlapping frame lines will be screwed tightly with a tie line. The pitch should not be greater than 50 mm, and the tie and lock method is as 2.3.