1. Install uprights. Column requirements are generally 2mm thick dip plastic steel pipes with a diameter of 60mm, which are fixed with embedded bolts and flange installation methods. Of course, there are also concrete pouring on site, but this is relatively rare. Note: The embedded base of the column must be flat, otherwise the installed guardrail will be deformed, and it will not even be installed. After the bolts are installed, the surface must be anti-corrosive. Note that it is better to use plastic impregnated columns, because the plastic impregnated columns have thick layers, long service life, and the best quality, followed by plastic sprayed and hot-dip galvanized steel pipe columns, and then galvanized and anti-rust paint. Of uprights.
2. Set up a mesh. Install the frame net directly on the column. This step requires at least 3-4 people to complete. If the sports fence net is high, there should be two levels, that is, the frame net between the two columns is two pieces above and below, and one piece should be past.